Calculated
Concrete Volume Calculator
Sign up to favourite this calculatorCalculate the volume of concrete needed for slabs, footings, columns and post holes, including a waste allowance and approximate bag quantities.
Includes a 10% waste allowance.
Bag quantities are estimates. Check the yield stated on your chosen product before buying.
For larger pours, compare the cost and effort of bagged concrete with ready-mix delivery.
This calculator provides an approximate material estimate only. Concrete requirements depend on ground conditions, project design, concrete specification, reinforcement and local building requirements. For structural work, foundations, retaining walls or work requiring Building Regulations or code approval, consult a qualified professional.
Sign in to keep your calculationsSaved · View in My dashboard
Saving…Saved to My dashboardCouldn't save. We'll try again.That saved calculation isn't available.
Share result
Compare scenarios
Keep this calculation as a scenario, change any input above, and the Now column shows how the result moves. Keep up to three, A to C; Open puts one back in the calculator.
Explain my result
Assumptions and limits
- An estimate from the numbers you entered, for guidance only. It is not financial, tax or medical advice.
- Calculator version 1, last updated 25 October 2026.
Was this calculator useful?
Report a problem
Saved to your account. Go to My dashboard to view your calculations.Link copied. Paste it wherever you want to share it.Your link is ready: open Share result and choose Copy link.
How to use this calculator
- Choose the project type, such as a slab, footing, column or post holes.
- Select Metric or Imperial measurements.
- Enter the relevant dimensions.
- Choose a waste allowance and bag option, if needed.
- The calculator estimates the concrete volume to order, plus approximate weight and bag quantities.
What do I need to enter?
- Measurement system — Metric (metres, millimetres, cubic metres) or Imperial (feet, inches, cubic yards). It also sets the result units and the bag options.
- Project type — Rectangular slab, Trench or strip footing, Circular column or pier, or Post holes. It decides which dimensions you are asked for.
- Length, Width and Depth — for a slab or footing. Each has its own unit, and must be greater than zero and no more than 100 m.
- Diameter and Height — for a column or pier.
- Hole diameter, Hole depth and Number of holes — for post holes. The volume of one hole is multiplied by the number of holes, which is one or more.
- Waste allowance — 0%, 5%, 10% or 15% added on top of the net volume.
- Bag or delivery option — a bag size, Ready-mix delivery or No bag estimate. Only a bag size produces a bag count.
What do the results show?
- Concrete to order — the main figure: net volume plus your waste allowance, in cubic metres or cubic yards.
- Net volume — the volume of the shape itself, before any waste allowance.
- Litres (metric) or Cubic feet (imperial) — the order volume in a second unit.
- Approximate weight — the order volume at about 2,400 kg per cubic metre, or 4,000 lb per cubic yard in imperial.
- Bag count — bags needed for the order volume, rounded up, using an estimated yield per bag. Check the packaging for the real yield.
How to calculate concrete volume
For a rectangular slab or footing, multiply length by width by depth. Make sure all measurements use the same unit before calculating.
- A circular column uses π × (diameter ÷ 2)² × height.
- Post holes use π × (diameter ÷ 2)² × depth × number of holes.
- Concrete to order = net volume × (1 + waste percentage ÷ 100).
Example: a 5 m × 3 m slab, 100 mm deep
- 100 mm is 0.1 m, so 5 × 3 × 0.1 = 1.5 m³ net volume.
- With a 10% waste allowance, 1.5 × 1.10 = 1.65 m³ to order.
- That is 1,650 litres and roughly 3.96 tonnes of concrete.
Metric and imperial concrete measurements
The calculator converts every measurement into a single internal volume before showing results in the selected measurement system.
| Metric | Imperial |
|---|---|
| Metres, centimetres and millimetres | Feet and inches |
| Cubic metres (m³) | Cubic yards (yd³) |
| Litres | Cubic feet (ft³) |
| 20 kg and 25 kg concrete bags | 40 lb, 60 lb and 80 lb concrete bags |
| Kilograms and tonnes | Pounds and US tons |
How much concrete waste should I allow?
A small waste allowance can help account for uneven ground, formwork variation, spillage and material left in a mixer. For straightforward work, 5% to 10% is often used as a starting estimate. Consider a higher allowance for irregular excavations, trenches, post holes or uneven ground.
Ready-mix concrete or bags?
Bagged concrete can be practical for small repairs, pads and individual post holes. For larger pours, ready-mix delivery may be more practical than transporting, mixing and placing many bags. Compare the total cost, delivery requirements, access and available labour before ordering.
Related tools
Need a compacted gravel sub-base before pouring? See the Gravel Calculator. Once a footing is poured, the Brick Calculator estimates the wall built on top of it.
Frequently asked questions
How do I calculate the amount of concrete I need?
How do I calculate concrete in cubic metres?
How do I calculate concrete in cubic yards?
How many litres are in one cubic metre?
How many cubic feet are in one cubic yard?
How many 25 kg bags of concrete make one cubic metre?
How many 80 lb bags of concrete make one cubic yard?
Should I add extra concrete for waste?
Can I use this calculator for foundations?
What thickness should my concrete slab be?
Last updated 25 October 2026.